The site sets the rhythm
Furniture can only be installed once walls, floors and services are finished. If it arrives too early it can be in the way or get damaged. If it arrives too late it delays handover.
Split the delivery by room or floor
On larger projects it makes sense to deliver per floor, department or room type, so each part arrives when the room is ready. This suits custom production well, where each part is made to measure anyway.
Measure to finished surfaces
Measuring should take place once the walls are built, so the furniture fits exactly. For each phase production can start as soon as the dimensions are settled.
Agree a plan together
Agree the order, access, interim storage and installation dates from the start. Delivery time for a project is typically 8 to 16 weeks, and with a plan later phases can follow while the first are already being installed.
The advantage of in house production
Because we produce ourselves, we can spread production over several phases and adjust the order if the construction programme changes.